Mirfa - Madinat Zayed Pipeline Pumping Stations, Reservoirs and Miscellaneous Works
The project was executed to transmit part of the desalinated water from a newly constructed desalination plant in Mirfa to Madinat Zayed a distance of over 60 Km through the desert with two intermediate pumping stations.

The project included the following construction activities:
Client: Abu Dhabi Water & Electricity Department
Contract Duration: 24 Months, completed in 1996
Scope of Works:
Project consisted mainly of the following:
a)Mirfa Central Pumping Station at Mirfa Central Desalination/Power Plant & Intermediate Pumping Stations 1 & 2
b)Detail design, engineering, supply, equipping, erection, construction, testing, commissioning etc. of complete pumping station installations for the pumping stations, including all necessary auxiliaries and ancillaries.
c)The pumping station at Mirfa Central Desalination/Power Plant and each of the Two intermediate pumping stations included an accommodation building for WED operating staff.
Reservoirs:
Detail design, engineering, supply, equipping, erection, construction, testing, commissioning etc. of a complete reinforced concrete break tank reservoirs of total capacity of 1,000,000 Imperial gallons each at intermediate pumping stations 1 and 2 and main reinforced concrete Reservoir constructions and installations comprising of 2 tanks, each of 2,000,000 Imperial Gallons at Madinat Zayed, Abu Dhabi.
Miscellaneous Works
Engineering, detail design, supply, installation, construction, testing etc. of miscellaneous civil works, pits, structures, road crossings sleeves, armour rock, sand, etc. along pipeline route (pipeline laid by WED).
Back to Past Projects
Gallery
© Copyright 2007
site by ayam creative
INFRASTRUCTURE
ELECTRICAL AND INSTRUMENTATION
MECHANICAL
SUBMARINE
IRRIGATION AND LANDSCAPING
CIVIL CONSTRUCTION
FABRICATION WORKSHOP
PAST
PRESENT