Scope of Works:
|
|
a) | Foundations for Desalination Units & Steam Transformers |
|
|
12 Desalination units and Steam Transformers.
|
|
b) | Switchgear Building for Desalination Units |
|
|
A building having dimensions of 37 m x 19 m with clear height of 3.6 m under roof beam.
|
|
c) | Piperacks |
|
|
Pipe and cable racks and construction of all foundation, grouting of embedded steel achors, painting of exposed concrete pedestals.
|
|
d) | Seawater supply, brine reject, distrillate and potable forwarding lines. |
|
|
Pipe handing, pipe preparation for lamination, pipe laying and lamination.
|
|
e) | Mooring Jetty |
|
|
Construction of temporary jetty for off loading of evaporators and heavy structures.
|
|
f) | Compressor Shelters |
|
|
Steel shelter to house the air compressor skids. |
|
g) | Potable Water Storage system |
|
|
Four (4) tanks, each of dia 90m, and operating capacity of 91,609 cum.
|
|
h) | Fire fighting protection system |
|
|
Firewater underground ring main lines, fire hydrants with hose cabinet. |
|
|
i) |
Spare Parts Storage Building |
|
|
j) |
Road & Paving |
|
|
k) |
Surface Water Drainage System |
|
|
l) |
Plant Waste Water Drainage System |
|
|
m) |
Street Lighting |
|
|
n) |
Electrical earthing buried grid system |
|
|
o) |
Plant communication |
|
|
p) |
Temporary facilities |
|
|