An Urgent Project undertaken by the Abu Dhabi Water & Electricity Authority to install water network lines for a new prestige housing development in the Eastern section of the Capital city of Abu Dhabi during the execution of the roads construction.
The project details are: |
|
Owner: Abu Dhabi Water & Electricity Authority (ADWEA)
|
Duration: 19/11/2002 to 18/11/2003
|
|
Scope of works: |
|
a) | Survey and prepare the existing and proposed pipeline installation shop drawings. |
|
b) | Supply and installation 800 mm ~ House connections DI water line pipes, fittings, valves & fire hydrants.
|
|
c) | Restore the grounds to their current conditions. |
|
d) | Coordinate the work with the Road Contractor assigned for the construction of the new roads.
|
|