An extension to the newly installed pipeline network at a major water pumping station in Abu Dhabi that serves the capital and the water network.
|
|
Client: Abu Dhabi Water & Electricity Authority
|
Contract Period: Completed on 2001 |
|
Scope of Works:
|
|
a) | Supply and install 1,000 mm DI water pipeline complete with fittings, valves, dismantling joints, strainers.
|
|
b) | Supply and install chlorination system for the additional works at Unit III.
|
|
c) | Supply and install electromagnetic flow meters on the line. |
|
d) | Supply and construct all civil works, valve chambers, non destructive road crossings and Oil & Gas line crossings along the pipeline rout. |
|
Testing and commissioning of the networks.
|
|
Back to Past Projects |
|
|
| |
|
|
|
|