Abu Dhabi Company for Onshore Operations (ADCO) has awarded the contract for the construction of a pumping station and a 36 KM HDPE pipeline through the desert to supply potable water to their facilities in Bab.
Al Nasr Irrigation & Contracting Co. was awarded the contract for the construction & commissioning of the pumping station and the pipeline as detailed hereby:
|
|
Client: Abu Dhabi Company for Onshore Operations
|
Contract Period: Completed in 1999
|
|
Scope of Works:
|
|
a) | Lay Ductile Cast iron pipeline of diameters 300mm, 250 mm and 200 mm between Madinat Zayed and Asab having a total length of 81 KM including for construction of pump house, chlorination building and substation at Madinat Zayed together with all controls, electrical and instrumentation works.
|
|
b) | Construction of pump station (1 No.) and panel water storage tanks (3 Nos.), erection of mechanical and electrical equipment with all necessary chambers, cabling, piping and instrumentation, testing and pre-commissioning and handing over to Client for commissioning.
|
|